A main road has reopened in Watford today after being closed for more than four months due to overrunning repairs to a bridge.

Water Lane has been closed since July 22 and had been due to reopen on September 13 but the finish date was pushed back to November as replacement parts for the bridge were delivered late.

The work was then delayed again into December due to bad weather.

It finally reopened at 3pm today.