Plans to extend the Metropolitan line have been put in doubt after Transport for London revealed a £50m black hole in funding for the project.

A letter seen by the Observer revealed that an extra £50m would be needed to complete the project, which will see the line extended to Watford Junction and Watford High Street stations.

SEE ALSO: Metropolitan Line Extension £50m short of budget

The letter from TfL’s head of London rail investment and LU line extensions Robert Niven to Conservative London Assembly member Gareth Bacon said TfL now estimated the project would cost £334m – and could not be delivered without the extra cash.

The Department for Transport has ruled out supplying any extra funding and said it expected the scheme to be delivered for £284m as agreed between TfL and the government in 2015.

Here is a timeline of everything you need to know about the project.

Watford Observer: In January, the Observer reported that TfL was looking into cost-cutting measures in the delivery of the scheme amid fears of a spiralling budget.

Under a funding agreement for the project set out in November 2015, TfL agreed to give £49m to support delivery, while local funding partners agreed to provide £125m and the DfT £109.8m.

The Mayor of London Sadiq Khan had written to transport secretary Chris Grayling regarding further discussions on how to take the project forward.

When plans for the project, known as the Croxley Rail Link, were first approved in 2011, it was expected to be delivered under the management of Hertfordshire County Council at a cost of £116.8m.

Watford Observer:

In November 2015, TfL took over the scheme after costs rose to £280m and the funding deal was agreed between the DfT, TfL and the council.

SEE ALSO: Met Line Extension: £130m of taxpayers' money spent on project

In December 2016, transport minister Andrew Jones ruled out the DfT providing any extra funding for the project and said it expected TfL to meet any expense above the £284.4m figure.

Taylor Woodrow beat Carillion and Bam Nuttall in 2013 to the contract to design and carry out enabling works for the project, with the contractor expected to clinch the main works deal.

But no contractor has been appointed to the main works and TfL confirmed in January they are looking into an alternative procurement plan amid the cost concerns.

Watford Observer:

TfL London Underground director of strategy David Hughes said: “Following this extensive work, we estimate that, to complete the extension, which is located outside of London, we would need to double the funding commitment we have already made, requiring more than an additional £50m that we are unable to provide.

“This does not mean the project has been cancelled and we remain open to helping assist the DfT in finding an alternative funding package for the project, or alternative schemes that may be more affordable.”

A DfT spokesman said: “Croxley Rail Link will deliver significant transport benefits and significantly boost economic growth in Watford and the wider north-west London area.

“We wrote to the mayor in January saying that we expect TfL to take forward the scheme in line with the agreements put in place in 2015. This remains our position.”

Almost £130m of taxpayers’ money has already been spent on the project, a Freedom of Information request revealed this week.